Wednesday, December 2, 2009

Wednesday, August 26, 2009

August 2009
















Here is an update of the project after it has had sometime to grow and root itself.

Sunday, July 12, 2009

Day 31




Finished!









































Last day! The roof is going up.

Day 30


Waiting for the roofing material. Gathered supplies and finished painting the structure.

Day 29
















Trusses going up.

Tuesday, July 7, 2009

DAY 28

We got the uprights in. It's starting to look like a stage.





Day 27

We got the rest of the sugar maples in today and put the wood on the trusses in the afternoon.


Saturday, July 4, 2009

Day 26











WE HAVE GRASS!










Sugar maples! We had three of the large sugar maples delivered today with the big tree spade. The rest will get put in Sunday. Fabrication on the roof went well today....with some help from Paul. Another hot sunny day. Keep the sprinklers on.

Day 25

Planted grass seed on the remaining mounds, and began working on roof fabrication. Cutting, grinding, welding.

Day 24




Set the rest of the granite benches and finished grading the mother mound.

Thursday, July 2, 2009

Day 23
















Tree day!!!!! Whitespire birch.

Day 22




Footings were poured today. and the granite delivered. Finished the stage roof uprights.

Monday, June 29, 2009

Day 21
















This fork lift can pick up 96000 lbs with out lifting the rear wheels off the ground, and it has no steering wheel just a joystick.












This is a big hole where the granite comes out of.

















Granite Day